Authored by Rystad Energy via OilPrice.com,
- Democratic governors will lead states accounting for 77% of the 300 GW of announced US data center capacity planned for 2027–2030.
- Rystad Energy forecasts 121 GW of additions during that period, with renewed Texas permitting restrictions potentially delaying approximately 3 GW.
- Tougher grid-connection requirements and long-term financial commitments could have a greater lasting impact on speculative projects than temporary permitting moratoria.
Starting in January, Democratic governors will lead US states that together hold 77% of the 300 gigawatts (GW) of data center capacity announced for 2027-2030, including the five largest markets: Texas, Virginia, Pennsylvania, Ohio and Georgia. Most of the winning candidates campaigned on making data centers pay their grid costs, rather than on stopping them, so the midterms are likely to change the terms of growth more than its pace.
Our risked forecast expects 121 GW to be added in 2027-2030, including about 49 GW of the 191 GW planned for 2029-30. Texas had implemented a permit pause but lifted it on November 17 at the behest of outgoing Governor Greg Abbott. Governor-elect Gina Hinojosa has pledged to implement a new one which, if it lasts until new rules take effect in September 2027, will delay about 3 GW of capacity. If the pauses are sustained for another year, over 10 GW is pushed back, and installed capacity at the end of 2029 would be about 170 GW instead of 177 GW.